Salton Europe Architect: Bower Mattin Ltd New 180,000ft² portal framed warehouse, 70m span propped portal, 17m to eaves, to be designed for VNA truck system on improved ground Using vibro compaction with piled foundations including diversion of culverted water course. Project programme 37 weeks build cost £8m
|