Clippers Quay, Salford

Project Overview

The construction of a new 614-unit residential development, Clippers Quay, is now complete.

Work commenced on site in early summer 2016 and completed in 2019,  with the main drainage installation, including sustainable drainage systems and a mixture of CFA and driven piles, which were specified to maximise efficiency to meet the specific needs of the building structure.

The new build to rent/private rental sector (PRS) project saw the creation of five high-quality, medium-rise buildings, constructed in durable and low-maintenance materials, with maximum opportunity taken to connect these with the Manchester Ship Canal which bounds two sides of the site. The scheme creates and maximises on external open space, with a mix of publicly accessible areas and private amenity space.

Detailed analysis and assessment of site constraints, resulted in coordinated design solutions which met the Client brief and cost plan.

Challenges/Solutions
  • The building structure utilises reinforced concrete with post-tensioned flat slabs floor structures. The first floor level facing Trafford Road is designed in traditional concrete to deal with a complex system of level changes, transfer elements and interfaces with the existing highway retaining wall. The design solution for the building has had to be finely adjusted to the project cost plan, with significant effort given to produce the most efficient frame for the scheme
  • Drainage, which includes sustainable on-site water storage and a negotiated outfall into the adjacent Manchester Ship Canal, is severely restricted by existing outfall points and the location of the site, however, our design has avoided the need for pumping stations
  • Coordination of the superstructure over first floor retail accommodation and ground floor car parking has presented a number of challenges which have been resolved with minimal transfer structure
  • With regard to the effect of the plot’s historical legacy ground conditions, the design of foundation solutions has also provided significant challenges, with zonal solutions and a mixture of piling techniques adopted to deliver a cost effective foundation design
  • The project included the retention and part-replacement of a section of existing highway retaining wall along the boundary of Trafford Road, which includes a Grade II-listed bridge control tower. Detailed negotiation with Salford City Council and Peel Ports resulted in the development of value engineered solutions

RoC Consulting remained an active member of the construction delivery team for civil and structural elements, following novation to main contractor Sir Robert McAlpine.  The project completed in early 2019.

Project Details
ProjectClippers Quay, Salford
DisciplineEarth Sciences, Structural Engineering
ClientAmstone
ArchitectLeach Rhodes Walker
Project Duration2014 - 2019
Value£80m
Through various challenges we have delivered the project a good few months earlier than our contract programme. That doesn’t happen by chance, it’s a team effort all around. We have found the RoC Consulting team proactive throughout, and easy to engage with. Steve Simpson BSc (Hons), Director - CIDON CONSTRUCTION
Download Project
Previous Project
Plot G Castlefield, Manchester
Next Project
Office 3 St. Paul's Place, Sheffield
Our Values
  • Listen We ensure that we listen to what our clients say about their needs, objectives, programme, resources and budget.
  • Understand We make sure that we understand the client’s brief, undertake rigorous analysis and challenge all assumptions.
  • Innovate We design practical, innovative solutions to minimise cost without sacrificing quality, so that money is spent where it matters.
  • Create Working closely with the design team and contractors, we deliver the client’s vision on time and on budget.
  • Deliver Our approach ensures that our clients trust us and are confident in our ability to deliver.

RoC Consulting
Fourways House
3rd Floor
Hilton Street
Manchester
M1 2EJ

0161 214 5390 info@rocconsulting.com

RoC Consulting
Get Directions

CitiPark - Dale Street
Get Directions

CitiPark - Tariffi Street
Get Directions

NCP Car Park - Store Street
Get Directions